In Zwijnaarde, Belgium, sewer operator Farys recently carried out a major sewer renovation in response to a damaged sewer manhole with severe infiltration issues. The project, executed by contractor Renotec, addressed a situation where the damage had caused subsidence in the surrounding roads, posing a direct threat to the infrastructure and the safety of local residents.
The water company - Farys - had clear requirements: the sewer manhole had to be completely watertight, and the existing dimensions had to be preserved as much as possible. All of this needed to be achieved with minimal disruption to residents and within the shortest possible execution time. Choosing the appropriate renovation technique was crucial to meeting these demands.
- Gianni Vancauwenberghe - Project Coordinator at Farys
- Elly Van der Schraelen - Project Manager at Renotec